Why this matters: the board has little time. One line says where we stand. The detail below backs it up, so nobody has to dig.
The permit resubmission is close. Two things need action now: ask PG&E about power early, and set a bigger cushion for surprises before the budget is approved.
Where we are
Permit submitted to the County May 22, 2026. Responses to County comments go back soon, together with the pricing set. Known
Kitchen layout, storage and the bread oven are being settled in meetings with YAC. Known
Commons & Burt are preparing a new estimate, expected around early December. Known
Build start April 24, 2027, about 51 weeks, finishing around April 2028. Assumed
Money
Decisions in the next 60 days
Biggest risks
What we ask of the board
Agree a target cushion for surprises before the budget is approved. Buildings like this often set aside 10 to 15% of construction. Research
Agree the dollar limit for small changes Anya can approve without the board.
Confirm whether the $2.8M funding plan includes the Olenta garage ADU. To check
Actions, team view
Decisions due
Why this matters: most delays on a build start as a decision made too late. Work back from the day something gets installed: subtract its lead time and review time, and you get the day we have to decide.
Dates marked suggested are a starting point to agree together. Build dates follow the contractor's rough timeline, starting April 24, 2027.
Decision log
Why this matters: decisions get recorded, not remembered. When people see it differently, we write down each view and the reasons, then the call and when we'll look at it again.
Foundation: mat slab or drilled piers
OpenLead: Anya
Options: a mat slab, or drilling deep for columns and piers. Both meet the soils report.
Where it stands: the geotech recommended both to the structural engineer on May 7. YAC leaned toward the mat slab. Anya to confirm.
Decision: not yet recorded.
Look again: before the permit resubmission.
Kitchen: regulated food facility or not
OpenLead: Anya
Options: build to food facility rules, or rely on the care-facility exclusion in state law. Research
Where it stands: no written answer from Environmental Health yet.
Decision: not yet recorded.
Look again: when the County's letter arrives.
Timeline
Why this matters: the timeline shows what has to happen before what. Orange marks the orders and choices that keep the build moving. When one slides, everything to its right can slide with it.
Planned workEstimate, to confirmOrder or chooseMilestoneRisk to watchCounty winter grading season (Oct 15 to Apr 15)
Build weeks come from the contractor's rough construction timeline. Assumed Scroll sideways on a phone.
Budget
Why this matters: money surprises are the most expensive kind. When every number shows where it came from, a gap shows up early, while there is still time to choose.
Estimate today
$2.41M
Commons & Burt ballpark, Jan 30, 2025, with owner costs. Known
Funding planned
$2.80M
Pro forma v1.3, Sept 25, 2026. The board has talked about $3M. Known
Cushion for surprises
$100.6k
About 4% of the estimate. Often 10 to 15% of construction. Research
Where the money goes
Item
Amount
Source
Contractor's work
$1,880,000
C&B ballpark Known
Contractor overhead and fee (18%)
$338,400
C&B ballpark Known
Owner costs: design, permits, fees, owner items
$191,600
Difference between the two totals Assumed
Community house estimate
$2,410,000
Olenta garage ADU, upper limit
$200,000
Peter, Nov 2026 Known
Both buildings
$2,610,000
Funding planned
$2,800,000
Pro forma v1.3 Known
Room left
$190,000
The cushion of $100.6k ($50.6k in the contractor's number, $50k in the owner budget) is already inside the estimate.
Try it: what if
Move the sliders to see how much room is left. These are what-ifs to talk through, not a forecast.
Room left
Risks
Why this matters: a risk named early is a choice. A risk named late is a cost. Each one has a first step we can take now.
Actions
Why this matters: a meeting only moves the build if someone does the next step. Here we see what is open as a team, so the next step is clear and nobody has to carry it in their head.
Ticks and new actions save for everyone on the team.
Changes
Why this matters: every change costs money, time or both. Writing each one down, with who asked and who said yes, keeps the cushion for surprises honest.
Cushion set aside
$100.6k
From the current estimate
Approved changes
$0
Cushion left
$100.6k
Small changes: Anya approves, under a limit we still need to agree. Big changes and use of the cushion: the board approves. New changes save for everyone on the team.
People and roles
Why this matters: when everyone knows who decides, who does the work, who we ask and who we keep in the loop, nobody waits and the contractor hears one voice.
Who has a stake
Person or team
Role on this build
Who does what
AHDecides: the one final say (A)
AWDoes: does the work (R)
PCAsked: before we decide (C)
BDTold: after we decide (I)
A first draft to agree together. Each task needs exactly one person who decides. Changes save for everyone on the team.